Methodology

Twenty-four months, three phases, ten work packages

The project runs for twenty-four months. The first phase sets the requirements, selects the winding concept and builds the modelling tools. The second turns them into a detailed design, a manufacturing route and a test platform. The third validates performance, safety and durability, and translates the results into a certification-readiness roadmap. Management and communication run continuously across all three.

Work plan

How the work packages connect

Phase 1 — Requirements and concept · M1–M8

Top-level aircraft and propulsion requirements are cascaded to system, motor, winding and material level. The winding concept is selected and the multiphysics modelling toolchain is built and benchmarked. Work packages WP2, WP3 and WP4.

Phase 2 — Design, manufacture and equip · M6–M18

Detailed winding and cryogenic cooling design, a repeatable and quality-controlled manufacturing route for representative modules, and a motor-representative test rig ready for the validation campaign. Work packages WP3, WP4, WP5 and WP6.

Phase 3 — Validate and consolidate · M9–M24

Electro-magneto-thermal testing, quench and fault response, lifecycle testing and system integration deliver the TRL5 evidence, followed by the certification-readiness assessment and the roadmap to TRL6. Work packages WP7, WP8 and WP9.

Continuous · M1–M24

WP1 management and coordination, and WP10 communication, dissemination and exploitation, run from M1 to M24.

Work packages

Ten work packages, eleven organisations

WP

Title

Lead

Months

WP1

Project management and coordination

UEDIN

M1–M24

WP2

Top-level requirements cascade

HPDRIVE

M1–M24

WP3

2 MW HTS motor and winding design

UEDIN

M1–M24

WP4

Cryo-cooling design and thermal management

POLIMI

M1–M13

WP5

HTS winding manufacturing route and repeatability

SUPRASYS

M1–M24

WP6

Motor-representative test-rig development

UNOTT

M1–M16

WP7

EMT and Lifecycle Testing of HTS Winding Modules

UL

M9–M22

WP8

System integration and testing

HPDRIVE

M13–M24

WP9

Certification readiness and TRL6 roadmap

HPDRIVE

M1–M24

WP10

Communication, dissemination and exploitation

SIE

M1–M24